Factory After Storage Mezzanine Floor Installation

Factory After Storage Mezzanine Floor Installation

When considering a mezzanine floor customers often worry about the time it takes to install the floor.  The lead times from order to delivery can be anywhere between 5 -7 weeks depending upon the time of year, with the 7 weeks being relevant around the Christmas and New Year bank holidays.

In terms of the installation itself, we normally advise customers to allow 1 day for every 60m2 that needs to be installed.  If fire protection is also required then that can add a further 1 day for every 60m2 of fire protection.  Of course every Cubex mezzanine floor is different;  a bespoke design to meet the requirements of our customers and their individual premises, however, using the above as guideline should help with necessary planning.

Many of our customers installing a mezzanine floor for the first time are concerned about the installation impacting their business.  At Cubex we support our customers by ensuring a robust project program is put in place as well as a disruption audit; giving customers visibility of what work is likely to be noisy or have an impact on their normal trading.  We have installed mezzanines over bank holidays weekends and evenings where necessary, to keep any disruption to a minimum.  If you want to know more about the process of installing a mezzanine floor please click on the following link to see our time lapse video and step by step images.